Select Year

Select Month

October 2023

Brigade Nanda Heights : Structure 16th floor completed 17th floor work in progress as on October '23

Brigade Nanda Heights : Structure 16th floor completed 17th floor work in progress

Brigade Nanda Heights : Water proofing works up to 5th floor completed 6th floor work in progress as on October '23

Brigade Nanda Heights : Water proofing works up to 5th floor completed 6th floor work in progress

September 2023

Brigade Nanda Heights : View from South Side (14th floor slab 100% completed 15th floor slab work in progress) as on September '23

Brigade Nanda Heights : View from South Side (14th floor slab 100% completed 15th floor slab work in progress)

Brigade Nanda Heights : Water proofing works up to 4th floor completed 5th floor work in progress as on September '23

Brigade Nanda Heights : Water proofing works up to 4th floor completed 5th floor work in progress

Brigade Nanda Heights : Milestone Release On Casting of Fourteenth floor slab as on September '23

Brigade Nanda Heights : Milestone Release On Casting of Fourteenth floor slab

August 2023

Brigade Nanda Heights Tower A : View From North Side (11th floor 100% completed 12th floor work in progress) as on August '23

Brigade Nanda Heights Tower A : View From North Side (11th floor 100% completed 12th floor work in progress)

Brigade Nanda Heights Tower A : Finishing Works and Water proofing works in progress up to 2nd floor as on August '23

Brigade Nanda Heights Tower A : Finishing Works and Water proofing works in progress up to 2nd floor

Brigade Nanda Heights : Milestone Release – On Casting of 9th Floor Slab as on August '23

Brigade Nanda Heights : Milestone Release – On Casting of 9th Floor Slab

July 2023

Brigade Nanda Heights Tower A : View From North Side (8th Floor 100% Completed 9th Floor work in progress) as on July '23

Brigade Nanda Heights Tower A : View From North Side (8th Floor 100% Completed 9th Floor work in progress)

Brigade Nanda Heights Tower A Structure : View From South Side (8th Floor Completed, 9th Floor work in progress) as on July '23

Brigade Nanda Heights Tower A Structure : View From South Side (8th Floor Completed, 9th Floor work in progress)

Brigade Nanda Heights Tower A : Finishing Works. And Water proofing works in progress up to 2nd floor as on July '23

Brigade Nanda Heights Tower A : Finishing Works. And Water proofing works in progress up to 2nd floor

June 2023

Brigade Nanda Heights Tower A : View From North Side (6th floor 100% completed. 7th floor work in progress) as on June '23

Brigade Nanda Heights Tower A : View From North Side (6th floor 100% completed. 7th floor work in progress)

Brigade Nanda Heights Tower A : View From South Side (6th floor completed, 7th floor work in progress) as on June '23

Brigade Nanda Heights Tower A : View From South Side (6th floor completed, 7th floor work in progress)

Brigade Nanda Heights Tower A : Finishing Works. Water proofing works in progress up to 2nd floor as on June '23

Brigade Nanda Heights Tower A : Finishing Works. Water proofing works in progress up to 2nd floor

Brigade Nanda Heights : Milestone Release – On Casting of 5th Floor Slab as on June '23

Brigade Nanda Heights : Milestone Release – On Casting of 5th Floor Slab

May 2023

Brigade Nanda Heights Tower A (view from North side) : 4th floor slab concreting 100% completed & 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from North side) : 4th floor slab concreting 100% completed & 5th floor works are in progress

Brigade Nanda Heights Tower A (view from East side) : 4th floor slab 100 % concreting works completed & 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from East side) : 4th floor slab 100 % concreting works completed & 5th floor works are in progress

Brigade Nanda Heights Tower A (view from  South side) : 4th floor slab conreting 100% completed & 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from South side) : 4th floor slab conreting 100% completed & 5th floor works are in progress

Brigade Nanda Heights Tower A (view from west side) : 4th floor slab 100% concreting completed and 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from west side) : 4th floor slab 100% concreting completed and 5th floor works are in progress

Brigade Nanda Heights Tower A (view from top) : 4th floor slab conreting 100% completed & 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from top) : 4th floor slab conreting 100% completed & 5th floor works are in progress

April 2023

Brigade Nanda Heights Tower A (view from North side) : 2nd floor slab concreting 100% completed & 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from North side) : 2nd floor slab concreting 100% completed & 3rd floor works are in progress

Brigade Nanda Heights Tower A (view from East side) : 2nd floor slab 100% concreting works completed & 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from East side) : 2nd floor slab 100% concreting works completed & 3rd floor works are in progress

Brigade Nanda Heights Tower A (view from  South side) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from South side) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress

Brigade Nanda Heights Tower A (view from west side) : 2nd floor slab 100% concreting completed and 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from west side) : 2nd floor slab 100% concreting completed and 3rd floor works are in progress

Brigade Nanda Heights Tower A (view from top) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from top) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress

March 2023

Brigade Nanda Heights Tower A (view from North side) : First floor slab concreting completed & podium slab concreting in progress as on March '23

Brigade Nanda Heights Tower A (view from North side) : First floor slab concreting completed & podium slab concreting in progress

Brigade Nanda Heights Tower A (view from  South side) : First floor slab conreting completed & 2nd floor works are in progress as on March '23

Brigade Nanda Heights Tower A (view from South side) : First floor slab conreting completed & 2nd floor works are in progress

Brigade Nanda Heights Tower A (view from East side) : First floor slab concreting works are completed & 2nd floor works are in progress  as on March '23

Brigade Nanda Heights Tower A (view from East side) : First floor slab concreting works are completed & 2nd floor works are in progress

Brigade Nanda Heights Tower A (view from west side): First floor slab concreting completed and 2nd floor works are in progress as on March '23

Brigade Nanda Heights Tower A (view from west side): First floor slab concreting completed and 2nd floor works are in progress

Brigade Nanda Heights Tower A: Milestone Release – On Casting of Ground Floor Slab as on March '23

Brigade Nanda Heights Tower A: Milestone Release – On Casting of Ground Floor Slab

February 2023

Brigade Nanda Heights Tower A (view from North side) : Ground floor works completed. Podium slab works are in progress as on February '23

Brigade Nanda Heights Tower A (view from North side) : Ground floor works completed. Podium slab works are in progress

Brigade Nanda Heights Tower A (view from East side) : Ground floor works completed & ready for concreting. Podium slab works are in progress  as on February '23

Brigade Nanda Heights Tower A (view from East side) : Ground floor works completed & ready for concreting. Podium slab works are in progress

Brigade Nanda Heights Tower A (view from  South side) : Ground floor works completed & ready for concreting as on February '23

Brigade Nanda Heights Tower A (view from South side) : Ground floor works completed & ready for concreting

Brigade Nanda Heights Tower A (view from west side) : Ground floor works completed and ready for concreting as on February '23

Brigade Nanda Heights Tower A (view from west side) : Ground floor works completed and ready for concreting

January 2023

Brigade Nanda Heights Tower A (view from North side) : Upper basement completed. Ground floor works are in progress as on January '23

Brigade Nanda Heights Tower A (view from North side) : Upper basement completed. Ground floor works are in progress

Brigade Nanda Heights Tower A (view from top) : Upper basement completed. Ground floor works are in progress as on January '23

Brigade Nanda Heights Tower A (view from top) : Upper basement completed. Ground floor works are in progress

Brigade Nanda Heights Tower A (view from East side) : Upper basement completed. Ground floor works are in progress as on January '23

Brigade Nanda Heights Tower A (view from East side) : Upper basement completed. Ground floor works are in progress

Brigade Nanda Heights Tower A (view from west side) : Upper basement completed. Ground floor sworks are in progress as on January '23

Brigade Nanda Heights Tower A (view from west side) : Upper basement completed. Ground floor sworks are in progress

October 2022

Brigade Nanda Heights : Milestone Release - On Casting of Footing/Raft as on October '22

Brigade Nanda Heights : Milestone Release - On Casting of Footing/Raft

Brigade Nanda Heights Tower A (view from North side) : Basement raft concreting completed & Upper basement slab works are in progress as on October '22

Brigade Nanda Heights Tower A (view from North side) : Basement raft concreting completed & Upper basement slab works are in progress

Brigade Nanda Heights Tower A (view from West side) : Upper basement slab works are in progress as on October '22

Brigade Nanda Heights Tower A (view from West side) : Upper basement slab works are in progress

Brigade Nanda Heights Tower A (view from East side) : Basement raft concreting completed & Upper basement slab works are in progress as on October '22

Brigade Nanda Heights Tower A (view from East side) : Basement raft concreting completed & Upper basement slab works are in progress

Brigade Nanda Heights Tower A (view from top) : Basement raft concreting completed & Upper basement slab works are in progress as on October '22

Brigade Nanda Heights Tower A (view from top) : Basement raft concreting completed & Upper basement slab works are in progress

November 2022

Tower A (view from North side) : Upper basement slab in progress & Ground floor vertical works are in progress as on November '22

Tower A (view from North side) : Upper basement slab in progress & Ground floor vertical works are in progress

Tower A (view from top) : Upper basement slab in progress and Ground floor verticals works are in progress as on November '22

Tower A (view from top) : Upper basement slab in progress and Ground floor verticals works are in progress

Tower A (view from East side): Upper basement slab in progress & Ground floor vertical works are in progress as on November '22

Tower A (view from East side): Upper basement slab in progress & Ground floor vertical works are in progress

Tower A (view from west side) : Upper basement slab in progress & Ground floor vertical works are in progress as on November '22

Tower A (view from west side) : Upper basement slab in progress & Ground floor vertical works are in progress

December 2022

Tower A (view from North side) : Upper basement slab concreting completed. Ground floor slab works are in progress as on December '22

Tower A (view from North side) : Upper basement slab concreting completed. Ground floor slab works are in progress

Tower A (view from top) : Upper basement slab concreting completed. Ground floor slab works are in  progress as on December '22

Tower A (view from top) : Upper basement slab concreting completed. Ground floor slab works are in progress

Tower A (view from East side) : Upper basement slab concreting completed. Ground floor slab works are in progress as on December '22

Tower A (view from East side) : Upper basement slab concreting completed. Ground floor slab works are in progress

Tower A (view from west side) : Upper basement slab concreting completed. Ground floor slab works are in progress as on December '22

Tower A (view from west side) : Upper basement slab concreting completed. Ground floor slab works are in progress

GET IN TOUCH

Write to our team of experts who will ensure you have a truly memorable experience from the simplest queries to elaborate property tours.

Or call us on
080 4647 4062

I Agree to the Terms and Conditions