Select Year

Select Month

January 2025

Brigade Nanda Heights : Milestone Release On Commencement of painting 18th to 23rd Floor as on January '25

Brigade Nanda Heights : Milestone Release On Commencement of painting 18th to 23rd Floor

Brigade Nanda Heights : Milestone Release On Commencement of painting 18th to 23rd Floor as on January '25

Brigade Nanda Heights : Milestone Release On Commencement of painting 18th to 23rd Floor

Brigade Nanda Heights : Milestone Release On Commencement of painting 18th to 23rd Floor as on January '25

Brigade Nanda Heights : Milestone Release On Commencement of painting 18th to 23rd Floor

December 2024

Brigade Nanda Heights as on December '24

Brigade Nanda Heights as on December '24

Brigade Nanda Heights : Finishing Works as on December '24

Brigade Nanda Heights : Finishing Works as on December '24

Brigade Nanda Heights : Finishing Works as on December '24

Brigade Nanda Heights : Finishing Works as on December '24

Brigade Nanda Heights : Finishing Works as on December '24

Brigade Nanda Heights : Finishing Works as on December '24

Brigade Nanda Heights : Common Area Finishing Works as on December '24

Brigade Nanda Heights : Common Area Finishing Works as on December '24

Brigade Nanda Heights : Common Area Finishing Works as on December '24

Brigade Nanda Heights : Common Area Finishing Works as on December '24

Brigade Nanda Heights : Common Area Finishing Works Entrance arch as on December '24

Brigade Nanda Heights : Common Area Finishing Works Entrance arch as on December '24

Brigade Nanda Heights : Common Area Finishing Works as on December '24

Brigade Nanda Heights : Common Area Finishing Works as on December '24

Brigade Nanda Heights : Common Area Finishing Works as on December '24

Brigade Nanda Heights : Common Area Finishing Works as on December '24

Brigade Nanda Heights : Common Area Finishing Works as on December '24

Brigade Nanda Heights : Common Area Finishing Works as on December '24

Brigade Nanda Heights Milestone Release –“On Commencement of fixing of doors & windows – 18th  to 23rd Floor” – Status as on 03rd December 2024

Milestone Release –“On Commencement of fixing of doors & windows – 18th to 23rd Floor” – Status as on 03rd December 2024

Brigade Nanda Heights Milestone Release –“On Commencement of fixing of doors & windows – 18th  to 23rd Floor” – Status as on 03rd December 2024

Milestone Release –“On Commencement of fixing of doors & windows – 18th to 23rd Floor” – Status as on 03rd December 2024

Brigade Nanda Heights Milestone Release –“On Commencement of fixing of doors & windows – 18th  to 23rd Floor” – Status as on 03rd December 2024

Milestone Release –“On Commencement of fixing of doors & windows – 18th to 23rd Floor” – Status as on 03rd December 2024

Brigade Nanda Heights Milestone Release –“On Commencement of fixing of doors & windows – 18th  to 23rd Floor” – Status as on 03rd December 2024

Milestone Release –“On Commencement of fixing of doors & windows – 18th to 23rd Floor” – Status as on 03rd December 2024

November 2024

Brigade Nanda Heights as on November '24

Brigade Nanda Heights

Brigade Nanda Heights as on November '24

Brigade Nanda Heights

Brigade Nanda Heights as on November '24

Finishing Works

Finishing Works as on November '24

Finishing Works

Common Area Finishing Works as on November '24

Finishing Works

Common Area Finishing Works as on November '24

Common Area Finishing Works

Common Area Finishing Works as on November '24

Common Area Finishing Works

Common Area Finishing Works Entrance arch as on November '24

Common Area Finishing Works Entrance arch

Common Area Finishing Works as on November '24

Common Area Finishing Works

Common Area Finishing Works as on November '24

Common Area Finishing Works

October 2024

Brigade Nanda Heights as on October '24

Brigade Nanda Heights

Brigade Nanda Heights : Finishing Works as on October '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on October '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Common Area Finishing Works. Entry portal & Basement VDF flooring as on October '24

Brigade Nanda Heights : Common Area Finishing Works. Entry portal & Basement VDF flooring

Brigade Nanda Heights : Milestone Release On Commencement of Flooring 18th to 23rd Floor as on October '24

Brigade Nanda Heights : Milestone Release On Commencement of Flooring 18th to 23rd Floor

Brigade Nanda Heights : Milestone Release On Commencement of Flooring 18th to 23rd Floor as on October '24

Brigade Nanda Heights : Milestone Release On Commencement of Flooring 18th to 23rd Floor

September 2024

Brigade Nanda Heights as on September '24

Brigade Nanda Heights

Brigade Nanda Heights : Finishing Works as on September '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on September '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on September '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Common Area Finishing Works as on September '24

Brigade Nanda Heights : Common Area Finishing Works

August 2024

Brigade Nanda Heights as on August '24

Brigade Nanda Heights

Brigade Nanda Heights : Finishing Works as on August '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on August '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on August '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Common Area Finishing Works as on August '24

Brigade Nanda Heights : Common Area Finishing Works

July 2024

Brigade Nanda Heights : Milestone Release On Commencement of Installation of Lifts as on July '24

Brigade Nanda Heights : Milestone Release On Commencement of Installation of Lifts

Brigade Nanda Heights : Finishing Works as on July '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on July '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on July '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Common Area Finishing Works as on July '24

Brigade Nanda Heights : Common Area Finishing Works

Brigade Nanda Heights : Common Area Finishing Works as on July '24

Brigade Nanda Heights : Common Area Finishing Works

Brigade Nanda Heights : Common Area Finishing Works as on July '24

Brigade Nanda Heights : Common Area Finishing Works

June 2024

Brigade Nanda Heights : Terrace slab completed. Above terrace works are in progress as on June '24

Brigade Nanda Heights : Terrace slab completed. Above terrace works are in progress

Brigade Nanda Heights : Finishing Works as on June '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on June '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on June '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Common Area Finishing Works as on June '24

Brigade Nanda Heights : Common Area Finishing Works

May 2024

Brigade Nanda Heights : Finishing Works as on May '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on May '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on May '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on May '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor as on May '24

Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor

Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor as on May '24

Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor

Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor as on May '24

Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor

April 2024

Brigade Nanda Heights : Finishing Works as on April '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on April '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on April '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on April '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Terrace slab completed, Above terrace works are in progress as on April '24

Brigade Nanda Heights : Terrace slab completed, Above terrace works are in progress

Brigade Nanda Heights : Milestone Release on commencement of Fixing of Doors & Windows Ground to 8th Floor as on April '24

Brigade Nanda Heights : Milestone Release on commencement of Fixing of Doors & Windows Ground to 8th Floor

Brigade Nanda Heights : Milestone Release on commencement of Fixing of Doors & Windows Ground to 8th Floor as on April '24

Brigade Nanda Heights : Milestone Release on commencement of Fixing of Doors & Windows Ground to 8th Floor

March 2024

Brigade Nanda Heights : Finishing Works as on March '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on March '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on March '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Structure 23rd floor completed, and Above terrace works are in progress as on March '24

Brigade Nanda Heights : Structure 23rd floor completed, and Above terrace works are in progress

February 2024

Brigade Nanda Heights : Milestone Release On Casting of Terrace slab as on February '24

Brigade Nanda Heights : Milestone Release On Casting of Terrace slab

Brigade Nanda Heights : Structure 23rd floor completed. Terrace floor slab works are in progress as on February '24

Brigade Nanda Heights : Structure 23rd floor completed. Terrace floor slab works are in progress

Brigade Nanda Heights : Finishing Works as on February '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on February '24

Brigade Nanda Heights : Finishing Works

January 2024

Brigade Nanda Heights : Structure 22nd floor completed. 23rd floor slab works are in progress as on January '24

Brigade Nanda Heights : Structure 22nd floor completed. 23rd floor slab works are in progress

Brigade Nanda Heights : Finishing Works as on January '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Finishing Works as on January '24

Brigade Nanda Heights : Finishing Works

Brigade Nanda Heights : Milestone Release On Casting of 21st Floor as on January '24

Brigade Nanda Heights : Milestone Release On Casting of 21st Floor

December 2023

Brigade Nanda Heights :  Structure 20th floor completed. 21st floor slab works are in progress as on December '23

Brigade Nanda Heights : Structure 20th floor completed. 21st floor slab works are in progress

Brigade Nanda Heights : Water proofing works up to 8th  floor completed 9th floor works are in progress as on December '23

Brigade Nanda Heights : Water proofing works up to 8th floor completed 9th floor works are in progress

Brigade Nanda Heights : Tiling works up to 3rd floor work in progress as on December '23

Brigade Nanda Heights : Tiling works up to 3rd floor work in progress

November 2023

Brigade Nanda Heights : Milestone Release – On Casting of Eighteenth Floor Slab as on November '23

Brigade Nanda Heights : Milestone Release – On Casting of Eighteenth Floor Slab

Brigade Nanda Heights : Finishing Works. Water proofing works up to 6th floor completed 7th floor works are in progress as on November '23

Brigade Nanda Heights : Finishing Works. Water proofing works up to 6th floor completed 7th floor works are in progress

Brigade Nanda Heights : Finishing Works. Tiling works commenced and entire 2nd floor completed as on November '23

Brigade Nanda Heights : Finishing Works. Tiling works commenced and entire 2nd floor completed

October 2023

Brigade Nanda Heights : Structure 16th floor completed 17th floor work in progress as on October '23

Brigade Nanda Heights : Structure 16th floor completed 17th floor work in progress

Brigade Nanda Heights : Water proofing works up to 5th floor completed 6th floor work in progress as on October '23

Brigade Nanda Heights : Water proofing works up to 5th floor completed 6th floor work in progress

September 2023

Brigade Nanda Heights : View from South Side (14th floor slab 100% completed 15th floor slab work in progress) as on September '23

Brigade Nanda Heights : View from South Side (14th floor slab 100% completed 15th floor slab work in progress)

Brigade Nanda Heights : Water proofing works up to 4th floor completed 5th floor work in progress as on September '23

Brigade Nanda Heights : Water proofing works up to 4th floor completed 5th floor work in progress

Brigade Nanda Heights : Milestone Release On Casting of Fourteenth floor slab as on September '23

Brigade Nanda Heights : Milestone Release On Casting of Fourteenth floor slab

August 2023

Brigade Nanda Heights Tower A : View From North Side (11th floor 100% completed 12th floor work in progress) as on August '23

Brigade Nanda Heights Tower A : View From North Side (11th floor 100% completed 12th floor work in progress)

Brigade Nanda Heights Tower A : Finishing Works and Water proofing works in progress up to 2nd floor as on August '23

Brigade Nanda Heights Tower A : Finishing Works and Water proofing works in progress up to 2nd floor

Brigade Nanda Heights : Milestone Release – On Casting of 9th Floor Slab as on August '23

Brigade Nanda Heights : Milestone Release – On Casting of 9th Floor Slab

July 2023

Brigade Nanda Heights Tower A : View From North Side (8th Floor 100% Completed 9th Floor work in progress) as on July '23

Brigade Nanda Heights Tower A : View From North Side (8th Floor 100% Completed 9th Floor work in progress)

Brigade Nanda Heights Tower A Structure : View From South Side (8th Floor Completed, 9th Floor work in progress) as on July '23

Brigade Nanda Heights Tower A Structure : View From South Side (8th Floor Completed, 9th Floor work in progress)

Brigade Nanda Heights Tower A : Finishing Works. And Water proofing works in progress up to 2nd floor as on July '23

Brigade Nanda Heights Tower A : Finishing Works. And Water proofing works in progress up to 2nd floor

June 2023

Brigade Nanda Heights Tower A : View From North Side (6th floor 100% completed. 7th floor work in progress) as on June '23

Brigade Nanda Heights Tower A : View From North Side (6th floor 100% completed. 7th floor work in progress)

Brigade Nanda Heights Tower A : View From South Side (6th floor completed, 7th floor work in progress) as on June '23

Brigade Nanda Heights Tower A : View From South Side (6th floor completed, 7th floor work in progress)

Brigade Nanda Heights Tower A : Finishing Works. Water proofing works in progress up to 2nd floor as on June '23

Brigade Nanda Heights Tower A : Finishing Works. Water proofing works in progress up to 2nd floor

Brigade Nanda Heights : Milestone Release – On Casting of 5th Floor Slab as on June '23

Brigade Nanda Heights : Milestone Release – On Casting of 5th Floor Slab

May 2023

Brigade Nanda Heights Tower A (view from North side) : 4th floor slab concreting 100% completed & 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from North side) : 4th floor slab concreting 100% completed & 5th floor works are in progress

Brigade Nanda Heights Tower A (view from East side) : 4th floor slab 100 % concreting works completed & 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from East side) : 4th floor slab 100 % concreting works completed & 5th floor works are in progress

Brigade Nanda Heights Tower A (view from  South side) : 4th floor slab conreting 100% completed & 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from South side) : 4th floor slab conreting 100% completed & 5th floor works are in progress

Brigade Nanda Heights Tower A (view from west side) : 4th floor slab 100% concreting completed and 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from west side) : 4th floor slab 100% concreting completed and 5th floor works are in progress

Brigade Nanda Heights Tower A (view from top) : 4th floor slab conreting 100% completed & 5th floor works are in progress as on May '23

Brigade Nanda Heights Tower A (view from top) : 4th floor slab conreting 100% completed & 5th floor works are in progress

April 2023

Brigade Nanda Heights Tower A (view from North side) : 2nd floor slab concreting 100% completed & 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from North side) : 2nd floor slab concreting 100% completed & 3rd floor works are in progress

Brigade Nanda Heights Tower A (view from East side) : 2nd floor slab 100% concreting works completed & 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from East side) : 2nd floor slab 100% concreting works completed & 3rd floor works are in progress

Brigade Nanda Heights Tower A (view from  South side) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from South side) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress

Brigade Nanda Heights Tower A (view from west side) : 2nd floor slab 100% concreting completed and 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from west side) : 2nd floor slab 100% concreting completed and 3rd floor works are in progress

Brigade Nanda Heights Tower A (view from top) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress as on April '23

Brigade Nanda Heights Tower A (view from top) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress

March 2023

Brigade Nanda Heights Tower A (view from North side) : First floor slab concreting completed & podium slab concreting in progress as on March '23

Brigade Nanda Heights Tower A (view from North side) : First floor slab concreting completed & podium slab concreting in progress

Brigade Nanda Heights Tower A (view from  South side) : First floor slab conreting completed & 2nd floor works are in progress as on March '23

Brigade Nanda Heights Tower A (view from South side) : First floor slab conreting completed & 2nd floor works are in progress

Brigade Nanda Heights Tower A (view from East side) : First floor slab concreting works are completed & 2nd floor works are in progress  as on March '23

Brigade Nanda Heights Tower A (view from East side) : First floor slab concreting works are completed & 2nd floor works are in progress

Brigade Nanda Heights Tower A (view from west side): First floor slab concreting completed and 2nd floor works are in progress as on March '23

Brigade Nanda Heights Tower A (view from west side): First floor slab concreting completed and 2nd floor works are in progress

Brigade Nanda Heights Tower A: Milestone Release – On Casting of Ground Floor Slab as on March '23

Brigade Nanda Heights Tower A: Milestone Release – On Casting of Ground Floor Slab

February 2023

Brigade Nanda Heights Tower A (view from North side) : Ground floor works completed. Podium slab works are in progress as on February '23

Brigade Nanda Heights Tower A (view from North side) : Ground floor works completed. Podium slab works are in progress

Brigade Nanda Heights Tower A (view from East side) : Ground floor works completed & ready for concreting. Podium slab works are in progress  as on February '23

Brigade Nanda Heights Tower A (view from East side) : Ground floor works completed & ready for concreting. Podium slab works are in progress

Brigade Nanda Heights Tower A (view from  South side) : Ground floor works completed & ready for concreting as on February '23

Brigade Nanda Heights Tower A (view from South side) : Ground floor works completed & ready for concreting

Brigade Nanda Heights Tower A (view from west side) : Ground floor works completed and ready for concreting as on February '23

Brigade Nanda Heights Tower A (view from west side) : Ground floor works completed and ready for concreting

January 2023

Brigade Nanda Heights Tower A (view from North side) : Upper basement completed. Ground floor works are in progress as on January '23

Brigade Nanda Heights Tower A (view from North side) : Upper basement completed. Ground floor works are in progress

Brigade Nanda Heights Tower A (view from top) : Upper basement completed. Ground floor works are in progress as on January '23

Brigade Nanda Heights Tower A (view from top) : Upper basement completed. Ground floor works are in progress

Brigade Nanda Heights Tower A (view from East side) : Upper basement completed. Ground floor works are in progress as on January '23

Brigade Nanda Heights Tower A (view from East side) : Upper basement completed. Ground floor works are in progress

Brigade Nanda Heights Tower A (view from west side) : Upper basement completed. Ground floor sworks are in progress as on January '23

Brigade Nanda Heights Tower A (view from west side) : Upper basement completed. Ground floor sworks are in progress

October 2022

Brigade Nanda Heights : Milestone Release - On Casting of Footing/Raft as on October '22

Brigade Nanda Heights : Milestone Release - On Casting of Footing/Raft

Brigade Nanda Heights Tower A (view from North side) : Basement raft concreting completed & Upper basement slab works are in progress as on October '22

Brigade Nanda Heights Tower A (view from North side) : Basement raft concreting completed & Upper basement slab works are in progress

Brigade Nanda Heights Tower A (view from West side) : Upper basement slab works are in progress as on October '22

Brigade Nanda Heights Tower A (view from West side) : Upper basement slab works are in progress

Brigade Nanda Heights Tower A (view from East side) : Basement raft concreting completed & Upper basement slab works are in progress as on October '22

Brigade Nanda Heights Tower A (view from East side) : Basement raft concreting completed & Upper basement slab works are in progress

Brigade Nanda Heights Tower A (view from top) : Basement raft concreting completed & Upper basement slab works are in progress as on October '22

Brigade Nanda Heights Tower A (view from top) : Basement raft concreting completed & Upper basement slab works are in progress

November 2022

Tower A (view from North side) : Upper basement slab in progress & Ground floor vertical works are in progress as on November '22

Tower A (view from North side) : Upper basement slab in progress & Ground floor vertical works are in progress

Tower A (view from top) : Upper basement slab in progress and Ground floor verticals works are in progress as on November '22

Tower A (view from top) : Upper basement slab in progress and Ground floor verticals works are in progress

Tower A (view from East side): Upper basement slab in progress & Ground floor vertical works are in progress as on November '22

Tower A (view from East side): Upper basement slab in progress & Ground floor vertical works are in progress

Tower A (view from west side) : Upper basement slab in progress & Ground floor vertical works are in progress as on November '22

Tower A (view from west side) : Upper basement slab in progress & Ground floor vertical works are in progress

December 2022

Tower A (view from North side) : Upper basement slab concreting completed. Ground floor slab works are in progress as on December '22

Tower A (view from North side) : Upper basement slab concreting completed. Ground floor slab works are in progress

Tower A (view from top) : Upper basement slab concreting completed. Ground floor slab works are in  progress as on December '22

Tower A (view from top) : Upper basement slab concreting completed. Ground floor slab works are in progress

Tower A (view from East side) : Upper basement slab concreting completed. Ground floor slab works are in progress as on December '22

Tower A (view from East side) : Upper basement slab concreting completed. Ground floor slab works are in progress

Tower A (view from west side) : Upper basement slab concreting completed. Ground floor slab works are in progress as on December '22

Tower A (view from west side) : Upper basement slab concreting completed. Ground floor slab works are in progress

GET IN TOUCH

Write to our team of experts who will ensure you have a truly memorable experience from the simplest queries to elaborate property tours.

Or call us on
080 4647 4062

I Agree to the Terms and Conditions