Select Year
Select Month
January 2025
Brigade Nanda Heights : Milestone Release On Commencement of painting 18th to 23rd Floor
Brigade Nanda Heights : Milestone Release On Commencement of painting 18th to 23rd Floor
Brigade Nanda Heights : Milestone Release On Commencement of painting 18th to 23rd Floor
December 2024
Brigade Nanda Heights as on December '24
Brigade Nanda Heights : Finishing Works as on December '24
Brigade Nanda Heights : Finishing Works as on December '24
Brigade Nanda Heights : Finishing Works as on December '24
Brigade Nanda Heights : Common Area Finishing Works as on December '24
Brigade Nanda Heights : Common Area Finishing Works as on December '24
Brigade Nanda Heights : Common Area Finishing Works Entrance arch as on December '24
Brigade Nanda Heights : Common Area Finishing Works as on December '24
Brigade Nanda Heights : Common Area Finishing Works as on December '24
Brigade Nanda Heights : Common Area Finishing Works as on December '24
Milestone Release –“On Commencement of fixing of doors & windows – 18th to 23rd Floor” – Status as on 03rd December 2024
Milestone Release –“On Commencement of fixing of doors & windows – 18th to 23rd Floor” – Status as on 03rd December 2024
Milestone Release –“On Commencement of fixing of doors & windows – 18th to 23rd Floor” – Status as on 03rd December 2024
Milestone Release –“On Commencement of fixing of doors & windows – 18th to 23rd Floor” – Status as on 03rd December 2024
November 2024
Brigade Nanda Heights
Brigade Nanda Heights
Finishing Works
Finishing Works
Finishing Works
Common Area Finishing Works
Common Area Finishing Works
Common Area Finishing Works Entrance arch
Common Area Finishing Works
Common Area Finishing Works
October 2024
Brigade Nanda Heights
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Common Area Finishing Works. Entry portal & Basement VDF flooring
Brigade Nanda Heights : Milestone Release On Commencement of Flooring 18th to 23rd Floor
Brigade Nanda Heights : Milestone Release On Commencement of Flooring 18th to 23rd Floor
September 2024
Brigade Nanda Heights
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Common Area Finishing Works
August 2024
Brigade Nanda Heights
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Common Area Finishing Works
July 2024
Brigade Nanda Heights : Milestone Release On Commencement of Installation of Lifts
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Common Area Finishing Works
Brigade Nanda Heights : Common Area Finishing Works
Brigade Nanda Heights : Common Area Finishing Works
June 2024
Brigade Nanda Heights : Terrace slab completed. Above terrace works are in progress
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Common Area Finishing Works
May 2024
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor
Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor
Brigade Nanda Heights : Milestone Release On commencement of Painting GF to 8th Floor
April 2024
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Terrace slab completed, Above terrace works are in progress
Brigade Nanda Heights : Milestone Release on commencement of Fixing of Doors & Windows Ground to 8th Floor
Brigade Nanda Heights : Milestone Release on commencement of Fixing of Doors & Windows Ground to 8th Floor
March 2024
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Structure 23rd floor completed, and Above terrace works are in progress
February 2024
Brigade Nanda Heights : Milestone Release On Casting of Terrace slab
Brigade Nanda Heights : Structure 23rd floor completed. Terrace floor slab works are in progress
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
January 2024
Brigade Nanda Heights : Structure 22nd floor completed. 23rd floor slab works are in progress
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Finishing Works
Brigade Nanda Heights : Milestone Release On Casting of 21st Floor
December 2023
Brigade Nanda Heights : Structure 20th floor completed. 21st floor slab works are in progress
Brigade Nanda Heights : Water proofing works up to 8th floor completed 9th floor works are in progress
Brigade Nanda Heights : Tiling works up to 3rd floor work in progress
November 2023
Brigade Nanda Heights : Milestone Release – On Casting of Eighteenth Floor Slab
Brigade Nanda Heights : Finishing Works. Water proofing works up to 6th floor completed 7th floor works are in progress
Brigade Nanda Heights : Finishing Works. Tiling works commenced and entire 2nd floor completed
October 2023
Brigade Nanda Heights : Structure 16th floor completed 17th floor work in progress
Brigade Nanda Heights : Water proofing works up to 5th floor completed 6th floor work in progress
September 2023
Brigade Nanda Heights : View from South Side (14th floor slab 100% completed 15th floor slab work in progress)
Brigade Nanda Heights : Water proofing works up to 4th floor completed 5th floor work in progress
Brigade Nanda Heights : Milestone Release On Casting of Fourteenth floor slab
August 2023
Brigade Nanda Heights Tower A : View From North Side (11th floor 100% completed 12th floor work in progress)
Brigade Nanda Heights Tower A : Finishing Works and Water proofing works in progress up to 2nd floor
Brigade Nanda Heights : Milestone Release – On Casting of 9th Floor Slab
July 2023
Brigade Nanda Heights Tower A : View From North Side (8th Floor 100% Completed 9th Floor work in progress)
Brigade Nanda Heights Tower A Structure : View From South Side (8th Floor Completed, 9th Floor work in progress)
Brigade Nanda Heights Tower A : Finishing Works. And Water proofing works in progress up to 2nd floor
June 2023
Brigade Nanda Heights Tower A : View From North Side (6th floor 100% completed. 7th floor work in progress)
Brigade Nanda Heights Tower A : View From South Side (6th floor completed, 7th floor work in progress)
Brigade Nanda Heights Tower A : Finishing Works. Water proofing works in progress up to 2nd floor
Brigade Nanda Heights : Milestone Release – On Casting of 5th Floor Slab
May 2023
Brigade Nanda Heights Tower A (view from North side) : 4th floor slab concreting 100% completed & 5th floor works are in progress
Brigade Nanda Heights Tower A (view from East side) : 4th floor slab 100 % concreting works completed & 5th floor works are in progress
Brigade Nanda Heights Tower A (view from South side) : 4th floor slab conreting 100% completed & 5th floor works are in progress
Brigade Nanda Heights Tower A (view from west side) : 4th floor slab 100% concreting completed and 5th floor works are in progress
Brigade Nanda Heights Tower A (view from top) : 4th floor slab conreting 100% completed & 5th floor works are in progress
April 2023
Brigade Nanda Heights Tower A (view from North side) : 2nd floor slab concreting 100% completed & 3rd floor works are in progress
Brigade Nanda Heights Tower A (view from East side) : 2nd floor slab 100% concreting works completed & 3rd floor works are in progress
Brigade Nanda Heights Tower A (view from South side) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress
Brigade Nanda Heights Tower A (view from west side) : 2nd floor slab 100% concreting completed and 3rd floor works are in progress
Brigade Nanda Heights Tower A (view from top) : 2nd floor slab conreting 100% completed & 3rd floor works are in progress
March 2023
Brigade Nanda Heights Tower A (view from North side) : First floor slab concreting completed & podium slab concreting in progress
Brigade Nanda Heights Tower A (view from South side) : First floor slab conreting completed & 2nd floor works are in progress
Brigade Nanda Heights Tower A (view from East side) : First floor slab concreting works are completed & 2nd floor works are in progress
Brigade Nanda Heights Tower A (view from west side): First floor slab concreting completed and 2nd floor works are in progress
Brigade Nanda Heights Tower A: Milestone Release – On Casting of Ground Floor Slab
February 2023
Brigade Nanda Heights Tower A (view from North side) : Ground floor works completed. Podium slab works are in progress
Brigade Nanda Heights Tower A (view from East side) : Ground floor works completed & ready for concreting. Podium slab works are in progress
Brigade Nanda Heights Tower A (view from South side) : Ground floor works completed & ready for concreting
Brigade Nanda Heights Tower A (view from west side) : Ground floor works completed and ready for concreting
January 2023
Brigade Nanda Heights Tower A (view from North side) : Upper basement completed. Ground floor works are in progress
Brigade Nanda Heights Tower A (view from top) : Upper basement completed. Ground floor works are in progress
Brigade Nanda Heights Tower A (view from East side) : Upper basement completed. Ground floor works are in progress
Brigade Nanda Heights Tower A (view from west side) : Upper basement completed. Ground floor sworks are in progress
October 2022
Brigade Nanda Heights : Milestone Release - On Casting of Footing/Raft
Brigade Nanda Heights Tower A (view from North side) : Basement raft concreting completed & Upper basement slab works are in progress
Brigade Nanda Heights Tower A (view from West side) : Upper basement slab works are in progress
Brigade Nanda Heights Tower A (view from East side) : Basement raft concreting completed & Upper basement slab works are in progress
Brigade Nanda Heights Tower A (view from top) : Basement raft concreting completed & Upper basement slab works are in progress
November 2022
Tower A (view from North side) : Upper basement slab in progress & Ground floor vertical works are in progress
Tower A (view from top) : Upper basement slab in progress and Ground floor verticals works are in progress
Tower A (view from East side): Upper basement slab in progress & Ground floor vertical works are in progress
Tower A (view from west side) : Upper basement slab in progress & Ground floor vertical works are in progress
December 2022
Tower A (view from North side) : Upper basement slab concreting completed. Ground floor slab works are in progress
Tower A (view from top) : Upper basement slab concreting completed. Ground floor slab works are in progress
Tower A (view from East side) : Upper basement slab concreting completed. Ground floor slab works are in progress
Tower A (view from west side) : Upper basement slab concreting completed. Ground floor slab works are in progress